Difference between revisions of "Cash flow model"
Cwhitehurst (talk | contribs) |
Cwhitehurst (talk | contribs) m (added Category:Methods in Exploration 10 using HotCat) |
||
(26 intermediate revisions by 3 users not shown) | |||
Line 15: | Line 15: | ||
==Data requirements== | ==Data requirements== | ||
− | The basis of economic evaluation of any proposed drilling venture—a new field, pool, or just a single well—is the ''cash flow model'' of investments, expenses, taxes, and wellhead revenues involved with the project. The values for the parameters in this model must come from a geotechnical analysis (including maps, cross | + | The basis of economic evaluation of any proposed drilling venture—a new field, pool, or just a single well—is the ''cash flow model'' of investments, expenses, taxes, and wellhead revenues involved with the project. The values for the parameters in this model must come from a geotechnical analysis (including maps, [[cross section]]s, and reservoir analysis) of the anticipated new field or well and from geotechnical estimates of area, ultimate recoverable reserves, and projected well production schedules. Here are the general data that are required: |
# All front end costs—leases, geology and geophysics (G & G), overhead, exploration drilling, and completion costs | # All front end costs—leases, geology and geophysics (G & G), overhead, exploration drilling, and completion costs | ||
− | # Projected dry hole costs | + | # Projected [[dry hole]] costs |
# Ultimate recoverable reserves (including secondary recovery) | # Ultimate recoverable reserves (including secondary recovery) | ||
# Field area (and thus number of producing wells), unless it's a single-well project | # Field area (and thus number of producing wells), unless it's a single-well project | ||
Line 44: | Line 44: | ||
:<math>\text{After-tax NOI} = (\text{Net revenue interest}~\times~\text{Production}~\times~\text{Wellhead price})</math> | :<math>\text{After-tax NOI} = (\text{Net revenue interest}~\times~\text{Production}~\times~\text{Wellhead price})</math> | ||
::<math>-~\text{Wellhead taxes}~-~\text{Operating costs}~-~\text{Federal income taxes} \ </math> | ::<math>-~\text{Wellhead taxes}~-~\text{Operating costs}~-~\text{Federal income taxes} \ </math> | ||
− | |||
− | |||
After the revenue and expenditure schedule has been determined, we can now calculate cash income taxes for our project. Finally, once the cash income taxes have been calculated for each year, the [[The time value of money|cash flow time diagram]] can be prepared and we are ready to calculate the net present value for our venture. | After the revenue and expenditure schedule has been determined, we can now calculate cash income taxes for our project. Finally, once the cash income taxes have been calculated for each year, the [[The time value of money|cash flow time diagram]] can be prepared and we are ready to calculate the net present value for our venture. | ||
Line 90: | Line 88: | ||
| '''NCF AFIT, $M''' || '''-1375.000''' || '''1359.098''' || '''578.462''' || '''314.450''' || '''168.376''' || '''87.377''' || '''44.916''' || '''19.417''' || '''4.795''' | | '''NCF AFIT, $M''' || '''-1375.000''' || '''1359.098''' || '''578.462''' || '''314.450''' || '''168.376''' || '''87.377''' || '''44.916''' || '''19.417''' || '''4.795''' | ||
|} | |} | ||
− | <sup>Source: After Thompson and Wright (1992)</sup><br> | + | :<sup>Source: After Thompson and Wright (1992)</sup><br> |
− | <sup>Assumed facts:</sup><br> | + | :<sup>Assumed facts:</sup><br> |
− | :<sup>Independent Producer and Royalty Owner status, therefore eligible for percentage depletion</sup><br> | + | ::<sup>Independent Producer and Royalty Owner status, therefore eligible for percentage depletion</sup><br> |
− | :<sup>NRI = 0.875, Wellhead tax on oil and gas revenue is 8%, annual operating cost is $24,000, incremental tax rate is 34%, oil price is $18/bbl, and gas price is $1.50/MCF</sup><br> | + | ::<sup>NRI = 0.875, Wellhead tax on oil and gas revenue is 8%, annual operating cost is $24,000, incremental tax rate is 34%, oil price is $18/bbl, and gas price is $1.50/MCF</sup><br> |
− | :<sup>Assumed Time 0 investments made on 1-1-91:</sup><br> | + | ::<sup>Assumed Time 0 investments made on 1-1-91:</sup><br> |
− | ::<sup>Lease Bonus and G&G (depletable basis for tax calculation) = $125,000</sup><br> | + | :::<sup>Lease Bonus and G&G (depletable basis for tax calculation) = $125,000</sup><br> |
− | ::<sup>IDC's (100 % expensed for tax calculation) = $950,000</sup><br> | + | :::<sup>IDC's (100 % expensed for tax calculation) = $950,000</sup><br> |
− | ::<sup>Tangible expenditures (depreciable basis for tax calculation) = $300,000</sup><br> | + | :::<sup>Tangible expenditures (depreciable basis for tax calculation) = $300,000</sup><br> |
− | :<sup>Estimated dry hole cost if the well is unsuccessful is $750,000 (After-tax = $750,000 x (1 - 0.34) = $495,000) | + | ::<sup>Estimated [[dry hole]] cost if the well is unsuccessful is $750,000 (After-tax = $750,000 x (1 - 0.34) = $495,000) |
A completed cash flow time diagram is shown in Table 2 along with the equivalent net present value calculation. | A completed cash flow time diagram is shown in Table 2 along with the equivalent net present value calculation. | ||
Line 127: | Line 125: | ||
|} | |} | ||
− | The same steps also apply to a multiwell project. Field development projects are constructed by combining individual well models in a realistic time frame. The income tax calculation must be done on a total project basis since oil and gas taxation applies to the total property. An example of a multiwell field extension project is shown in Table 3. | + | The same steps also apply to a multiwell project. Field development projects are constructed by combining individual well models in a realistic time frame. The income tax calculation must be done on a total project basis since oil and gas taxation applies to the total property. An example of a multiwell field extension project is shown in Table 3. Since the project has a longer life than the example development well, the results are summarized in a slightly different format. The production, investment, and tax assumptions for the multiwell extension project are outlined below the table. |
{| class="wikitable" | {| class="wikitable" | ||
Line 156: | Line 154: | ||
| 2001 || 0.168 || 0.084 || 500 || 0.147 || 0.073 || 18.00 || 1.50 || 2.642 || 0.110 || 2.752 | | 2001 || 0.168 || 0.084 || 500 || 0.147 || 0.073 || 18.00 || 1.50 || 2.642 || 0.110 || 2.752 | ||
|- | |- | ||
− | | '''Totals''' || '''839.566''' || '''419.783''' || '''500''' || '''734.621''' || '''367.10''' | + | | '''Totals''' || '''839.566''' || '''419.783''' || '''500''' || '''734.621''' || '''367.10''' || || || || || |
|} | |} | ||
{| class="wikitable" | {| class="wikitable" | ||
Line 189: | Line 187: | ||
| '''Totals''' || '''680.632''' || '''1101.931''' || '''11991.572''' || '''7225.000''' || '''4766.572''' || '''1131.851''' || '''3634.721''' || || '''2729.760''' || || '''6859.396''' | | '''Totals''' || '''680.632''' || '''1101.931''' || '''11991.572''' || '''7225.000''' || '''4766.572''' || '''1131.851''' || '''3634.721''' || || '''2729.760''' || || '''6859.396''' | ||
|} | |} | ||
− | + | <sup>'''Assumptions for Example Multiwell Extension Project'''</sup><br> | |
− | + | :<sup>NRI = 0.875</sup><br> | |
+ | :<sup>Wellhead tax on oil and gas revenue is 8%</sup><br> | ||
+ | :<sup>Annual operating cost is $24,000/well. Note in the last four years the operating costs are not a multiple of $24,000. This is because the typical well produces only a fraction of a year in the eighth year.</sup><br> | ||
+ | :<sup>Incremental tax rate is 34%</sup><br> | ||
+ | :<sup>Oil price is $18.00/bbl. Gas price is $1.50/MCF</sup><br> | ||
+ | :<sup>Cost of Failure is assumed to be the after tax cost of 2 [[dry hole]]s.</sup><br> | ||
+ | ::<sup>(750,000 x (1 - 0.34) x 2 = $990,000)</sup><br> | ||
+ | :<sup>Assumed investment schedule:</sup><br> | ||
+ | ::<sup>Time 0 investments made on 1-1-91:</sup><br> | ||
+ | :::<sup>Lease bonus and G&G = $125,000</sup><br> | ||
+ | :::<sup>IDC's (100% expensed for tax calculation) = $950,000 (for one completion)</sup><br> | ||
+ | :::<sup>Tangible expenditures (depreciable basis for tax calculation) = $300,000</sup><br> | ||
+ | ::<sup>Other investments made during 1991:</sup><br> | ||
+ | :::<sup>Lease bonus and G&G = $200,000</sup><br> | ||
+ | :::<sup>IDC's (100% expensed for tax calculation) = $950,000 (for one completion)</sup><br> | ||
+ | :::<sup>DHC's (100% expensed for tax calculation) = $1,500,000 (for two dry holes)</sup><br> | ||
+ | :::<sup>Tangible expenditures (depreciable basis for tax calculation) = $600,000</sup><br> | ||
+ | ::<sup>Investments made during 1992:</sup><br> | ||
+ | :::<sup>Lease bonus and G&G = $100,000</sup><br> | ||
+ | :::<sup>IDC's (100% expensed for tax calculation) = $950,000 (for one completion)</sup><br> | ||
+ | :::<sup>Tangible expenditures (depreciable basis for tax calculation) = $300,000</sup><br> | ||
+ | ::<sup>Investments made during 1993:</sup><br> | ||
+ | :::<sup>IDC's (100% expensed for tax calculation) = $950,000 (for one completion)</sup><br> | ||
+ | :::<sup>Tangible expenditures (depreciable basis for tax calculation) = $300,000</sup><br> | ||
+ | :<sup>Assumed Production Schedule</sup><br> | ||
+ | ::<sup>The production forecast for the typical well in the Example Development Well was used for the Multiwell Extension Project. A typical well was assumed to be placed on production at the beginning of each of the years 1991, 1992, 1993, and 1994.</sup><br> | ||
+ | {{clear}} | ||
==Points to remember== | ==Points to remember== | ||
Here are a few final points that are important to remember concerning cash flow models: | Here are a few final points that are important to remember concerning cash flow models: | ||
− | # Cash flow analysis is the third step in evaluating a proposed (or existing) petroleum property; it occurs after estimating (a) the reserves, rates, and costs and (b) the chance of success. | + | # Cash flow analysis is the third step in evaluating a proposed (or existing) [[petroleum]] property; it occurs after estimating (a) the reserves, rates, and costs and (b) the chance of success. |
# Do not carry out cash flow analysis of "risked reserves"—the cash flow model is built on the success case | # Do not carry out cash flow analysis of "risked reserves"—the cash flow model is built on the success case | ||
# Net cash flow is the sum of outlays and inflows. | # Net cash flow is the sum of outlays and inflows. | ||
Line 210: | Line 234: | ||
==See also== | ==See also== | ||
− | * [[ | + | * [[Risk: expected value and chance of success]] |
− | * [[ | + | * [[Economics: time value of money]] |
− | * [[ | + | * [[Risk: dealing with risk aversion]] |
− | * [[ | + | * [[Economics: fundamental equations for oil and gas property evaluation]] |
− | * [[ | + | * [[Economics: key parameters]] |
* [[Economics of property acquisitions]] | * [[Economics of property acquisitions]] | ||
− | * [[ | + | * [[Taxes]] |
* [[Introduction to economics and risk assessment]] | * [[Introduction to economics and risk assessment]] | ||
* [[Uncertainties impacting reserves, revenue, and costs]] | * [[Uncertainties impacting reserves, revenue, and costs]] | ||
Line 229: | Line 253: | ||
[[Category:Economics and risk assessment]] [[Category:Pages with unformatted equations]] | [[Category:Economics and risk assessment]] [[Category:Pages with unformatted equations]] | ||
+ | [[Category:Methods in Exploration 10]] |
Latest revision as of 19:27, 19 January 2022
Intro should go here
Data requirements[edit]
The basis of economic evaluation of any proposed drilling venture—a new field, pool, or just a single well—is the cash flow model of investments, expenses, taxes, and wellhead revenues involved with the project. The values for the parameters in this model must come from a geotechnical analysis (including maps, cross sections, and reservoir analysis) of the anticipated new field or well and from geotechnical estimates of area, ultimate recoverable reserves, and projected well production schedules. Here are the general data that are required:
- All front end costs—leases, geology and geophysics (G & G), overhead, exploration drilling, and completion costs
- Projected dry hole costs
- Ultimate recoverable reserves (including secondary recovery)
- Field area (and thus number of producing wells), unless it's a single-well project
- Typical well production schedules, including initial production, decline rate, and producing life to abandonment
- All development costs, classified for tax calculations as either tangible expenditures or intangible drilling and development costs (IDCs), and scheduled by the month and year
- Annual operating cost per well
- Wellhead prices, wellhead taxes, and transportation costs
- Abandonment costs
- Annual federal income taxes. The model can be adapted for the analysis of international prospects by changing this item in the cash flow model to "outsider's take." Simply apply the tax rules for that country.
- Anticipated price or cost escalation schedule, if any (the example shown in Table 1 uses the constant dollar concept, thus no price or cost escalation schedule is provided). Inflation (loss of purchasing power) is also assumed to be zero.
- Net revenue interest (NRI) of lease (1.00 - royalty interest) and company share of working interest
- Company discount rate
- Anticipated incremental income tax rate
The procedure is basically to plan out the life of the field, project, or well from the first expenditure through abandonment, assigning costs and revenues to events and dates.
Calculations in the cash flow model[edit]
The net cash flow (NCF) for each assumed time period, including time 0, can be determined using the following equation.
Some of the economic parameters presented later utilize after-tax net operating income (NOI) as a measure of profit. After-tax NOI is defined as follows:
After the revenue and expenditure schedule has been determined, we can now calculate cash income taxes for our project. Finally, once the cash income taxes have been calculated for each year, the cash flow time diagram can be prepared and we are ready to calculate the net present value for our venture.
For now, let's assume we are provided the cash income tax number, so we are ready to look at an example problem for a single development well. The assumptions for this example problem and a completed worksheet are presented in Table 1.
Cash Flow Worksheet | |||||||||
---|---|---|---|---|---|---|---|---|---|
Year | 0 | 1991 | 1992 | 1993 | 1994 | 1995 | 1996 | 1997 | 1998 |
ASSUMED FACTS | |||||||||
Gross Oil Prod MBO | 0.000 | 96.066 | 52.722 | 28.934 | 15.880 | 8.715 | 4.783 | 2.625 | 0.168 |
Gross Gas Prod MMCF | 0.000 | 48.033 | 26.361 | 14.467 | 7.940 | 4.357 | 2.391 | 1.312 | 0.084 |
Working Interest | 1.000 | 1.000 | 1.000 | 1.000 | 1.000 | 1.000 | 1.000 | 1.000 | 1.000 |
Net Revenue Interest | 0.875 | 0.875 | 0.875 | 0.875 | 0.875 | 0.875 | 0.875 | 0.875 | 0.87 |
Oil Prices $/bbl | 18.000 | 18.000 | 18.000 | 18.000 | 18.000 | 18.000 | 18.000 | 18.000 | 18.000 |
Gas Prices $/MCF | 1.500 | 1.500 | 1.500 | 1.500 | 1.500 | 1.500 | 1.500 | 1.500 | 1.500 |
CALCULATIONS | |||||||||
Gross Income, $M | 0.000 | 1576.075 | 864.968 | 474.705 | 260.503 | 142.978 | 78.468 | 43.064 | 2.752 |
—Operating Costs, $M | 0.000 | 24.000 | 24.000 | 24.000 | 24.000 | 24.000 | 24.000 | 24.000 | 24.000 |
—Sev.Adv. Tax, $M | 0.000 | 126.086 | 69.197 | 37.976 | 20.842 | 11.438 | 6.277 | 3.445 | 0.220 |
NOI BFIT, $M | 0.000 | 1425.989 | 771.771 | 412.728 | 215.682 | 107.540 | 48.191 | 15.619 | 0.373 |
—Cash Taxes, $M | 0.000 | 66.891 | 193.309 | 98.278 | 47.305 | 20.163 | 3.274 | -3.798 | -4.422 |
NOI AFIT, $M | 0.000 | 1359.098 | 578.462 | 314.450 | 168.376 | 87.377 | 44.916 | 19.417 | 4.795 |
—Investment, $M | 1375.000 | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 |
NCF AFIT, $M | -1375.000 | 1359.098 | 578.462 | 314.450 | 168.376 | 87.377 | 44.916 | 19.417 | 4.795 |
- Source: After Thompson and Wright (1992)
- Assumed facts:
- Independent Producer and Royalty Owner status, therefore eligible for percentage depletion
- NRI = 0.875, Wellhead tax on oil and gas revenue is 8%, annual operating cost is $24,000, incremental tax rate is 34%, oil price is $18/bbl, and gas price is $1.50/MCF
- Assumed Time 0 investments made on 1-1-91:
- Lease Bonus and G&G (depletable basis for tax calculation) = $125,000
- IDC's (100 % expensed for tax calculation) = $950,000
- Tangible expenditures (depreciable basis for tax calculation) = $300,000
- Lease Bonus and G&G (depletable basis for tax calculation) = $125,000
- Estimated dry hole cost if the well is unsuccessful is $750,000 (After-tax = $750,000 x (1 - 0.34) = $495,000)
- Independent Producer and Royalty Owner status, therefore eligible for percentage depletion
A completed cash flow time diagram is shown in Table 2 along with the equivalent net present value calculation.
Time | Cash Flow | Discount Factor | Present Value |
---|---|---|---|
0 | $-1375 | 1.0000 | $-1375.0 |
1 | 1359.098 | 0.9615 | 1306.8 |
2 | 578.462 | 0.9246 | 534.8 |
3 | 314.450 | 0.8890 | 279.5 |
4 | 168.376 | 0.8548 | 143.9 |
5 | 87.377 | 0.8219 | 71.8 |
6 | 44.916 | 0.7903 | 35.5 |
7 | 19.417 | 0.7599 | 14.8 |
8 | 4.795 | 0.7307 | 3.5 |
Project NPV | $1015.6 |
The same steps also apply to a multiwell project. Field development projects are constructed by combining individual well models in a realistic time frame. The income tax calculation must be done on a total project basis since oil and gas taxation applies to the total property. An example of a multiwell field extension project is shown in Table 3. Since the project has a longer life than the example development well, the results are summarized in a slightly different format. The production, investment, and tax assumptions for the multiwell extension project are outlined below the table.
Year | Gross Oil Production (Mbbl) | Gross Gas Production (MMSCF) | Gas-Oil Ratio (SF/STB) | XYZ Oil Co. Net Oil Production (Mbbl) | XYZ Oil Co. Net Gas Production (MMSCF) | Oil Price ($/bbl) | Gas Price ($MCF) | XYZ Oil Co. Oil Income ($M) | XYZ Oil Co. Gas Income ($M) | XYZ Oil Co. Gross Income ($M) |
---|---|---|---|---|---|---|---|---|---|---|
1991 | 96.066 | 48.033 | 500 | 84.057 | 42.029 | 18.00 | 1.50 | 1513.032 | 63.043 | 1576.075 |
1992 | 148.787 | 74.394 | 500 | 130.189 | 65.094 | 18.00 | 1.50 | 2343.402 | 97.642 | 2441.043 |
1993 | 177.72 | 88.861 | 500 | 155.507 | 77.753 | 18.00 | 1.50 | 2799.118 | 116.630 | 2915.748 |
1994 | 193.601 | 96.801 | 500 | 169.401 | 84.701 | 18.00 | 1.50 | 3049.221 | 127.051 | 3176.271 |
1995 | 106.251 | 53.125 | 500 | 92.969 | 46.485 | 18.00 | 1.50 | 1673.448 | 69.727 | 1743.175 |
1996 | 58.312 | 29.156 | 500 | 51.023 | 25.511 | 18.00 | 1.50 | 918.408 | 38.267 | 956.675 |
1997 | 32.002 | 16.001 | 500 | 28.002 | 14.001 | 18.00 | 1.50 | 504.033 | 21.001 | 525.034 |
1998 | 16.290 | 8.145 | 500 | 14.254 | 7.127 | 18.00 | 1.50 | 256.572 | 10.690 | 267.262 |
1999 | 7.575 | 3.788 | 500 | 6.628 | 3.314 | 18.00 | 1.50 | 119.313 | 4.971 | 124.284 |
2000 | 2.793 | 1.396 | 500 | 2.444 | 1.222 | 18.00 | 1.50 | 43.983 | 1.833 | 45.816 |
2001 | 0.168 | 0.084 | 500 | 0.147 | 0.073 | 18.00 | 1.50 | 2.642 | 0.110 | 2.752 |
Totals | 839.566 | 419.783 | 500 | 734.621 | 367.10 |
Year | XYZ Oil Company | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Operating Costs ($M) | State + Local Tax ($M) | Net Oper. Inc BFIT ($M) | Total Cash Invest ($M) | Net Cash Flow BFIT ($M) | Fed. Inc. Tax ($M) | Net Cash Flow AFIT ($M) | Cum. NCF AFIT ($M) | Disc. NCF AFIT @ 4% ($M) | Cum. Disc. NCF AFIT @ 4% ($M) | Disc. Invest @ 4% ($M) | |
0 | 1375.000 | -1375.000 | -1375.000 | -1375.000 | -1375.000 | -1375.000 | 1375.000 | ||||
1991 | 24.000 | 126.086 | 1425.989 | 3250.000 | -1824.011 | -727.504 | -1096.507 | -2471.507 | -1054.333 | -2429.333 | 3125.000 |
1992 | 48.000 | 195.283 | 2197.760 | 1350.000 | 847.760 | 210.240 | 637.520 | -1833.987 | 589.423 | -1839.911 | 1248.151 |
1993 | 72.000 | 233.260 | 2610.488 | 1250.000 | 1360.488 | 322.798 | 1037.690 | -796.297 | 922.503 | -917.408 | 1111.245 |
1994 | 96.000 | 254.102 | 2826.170 | 0.000 | 2826.170 | 717.869 | 2108.301 | 1312.004 | 1802.184 | 884.776 | 0.000 |
1995 | 96.000 | 139.454 | 1507.721 | 0.000 | 1507.721 | 365.818 | 1141.903 | 2453.907 | 938.561 | 1823.337 | 0.000 |
1996 | 96.000 | 76.534 | 784.141 | 0.000 | 784.141 | 168.643 | 615.497 | 3069.404 | 486.437 | 2309.774 | 0.000 |
1997 | 96.000 | 42.003 | 387.031 | 0.000 | 387.031 | 59.271 | 327.760 | 3397.165 | 249.071 | 2558.845 | 0.000 |
1998 | 74.158 | 21.381 | 171.723 | 0.000 | 171.723 | 12.891 | 158.833 | 3555.997 | 116.057 | 2674.902 | 0.000 |
1999 | 50.158 | 9.943 | 64.183 | 0.000 | 64.183 | 1.826 | 62.357 | 3618.355 | 43.811 | 2718.714 | 0.000 |
2000 | 26.158 | 3.665 | 15.993 | 0.000 | 15.993 | 0.000 | 15.993 | 3634.347 | 10.804 | 2729.518 | 0.000 |
2001 | 2.158 | 0.220 | 0.374 | 0.000 | 0.374 | 0.000 | 0.374 | 3634.721 | 0.243 | 2729.760 | 0.000 |
Totals | 680.632 | 1101.931 | 11991.572 | 7225.000 | 4766.572 | 1131.851 | 3634.721 | 2729.760 | 6859.396 |
Assumptions for Example Multiwell Extension Project
- NRI = 0.875
- Wellhead tax on oil and gas revenue is 8%
- Annual operating cost is $24,000/well. Note in the last four years the operating costs are not a multiple of $24,000. This is because the typical well produces only a fraction of a year in the eighth year.
- Incremental tax rate is 34%
- Oil price is $18.00/bbl. Gas price is $1.50/MCF
- Cost of Failure is assumed to be the after tax cost of 2 dry holes.
- (750,000 x (1 - 0.34) x 2 = $990,000)
- (750,000 x (1 - 0.34) x 2 = $990,000)
- Assumed investment schedule:
- Time 0 investments made on 1-1-91:
- Lease bonus and G&G = $125,000
- IDC's (100% expensed for tax calculation) = $950,000 (for one completion)
- Tangible expenditures (depreciable basis for tax calculation) = $300,000
- Lease bonus and G&G = $125,000
- Other investments made during 1991:
- Lease bonus and G&G = $200,000
- IDC's (100% expensed for tax calculation) = $950,000 (for one completion)
- DHC's (100% expensed for tax calculation) = $1,500,000 (for two dry holes)
- Tangible expenditures (depreciable basis for tax calculation) = $600,000
- Lease bonus and G&G = $200,000
- Investments made during 1992:
- Lease bonus and G&G = $100,000
- IDC's (100% expensed for tax calculation) = $950,000 (for one completion)
- Tangible expenditures (depreciable basis for tax calculation) = $300,000
- Lease bonus and G&G = $100,000
- Investments made during 1993:
- IDC's (100% expensed for tax calculation) = $950,000 (for one completion)
- Tangible expenditures (depreciable basis for tax calculation) = $300,000
- IDC's (100% expensed for tax calculation) = $950,000 (for one completion)
- Time 0 investments made on 1-1-91:
- Assumed Production Schedule
- The production forecast for the typical well in the Example Development Well was used for the Multiwell Extension Project. A typical well was assumed to be placed on production at the beginning of each of the years 1991, 1992, 1993, and 1994.
- The production forecast for the typical well in the Example Development Well was used for the Multiwell Extension Project. A typical well was assumed to be placed on production at the beginning of each of the years 1991, 1992, 1993, and 1994.
Points to remember[edit]
Here are a few final points that are important to remember concerning cash flow models:
- Cash flow analysis is the third step in evaluating a proposed (or existing) petroleum property; it occurs after estimating (a) the reserves, rates, and costs and (b) the chance of success.
- Do not carry out cash flow analysis of "risked reserves"—the cash flow model is built on the success case
- Net cash flow is the sum of outlays and inflows.
- Any investment is a purchase of anticipated future annual cash flows.
- A permanent alternative to any petroleum venture is to put the investment capital "in the bank" (that is, alternative safe investments), where it will earn regular interest at the corporate rate.
- If prices and costs are assumed to be in terms of constant purchasing power, then the discount component should only include the real interest component. The inflation component should not be included. If the prices and costs are escalated, then the discount rate selected should include the real interest rate and the inflation component.
- Higher discount rates tend to favor shorter term and lower dollar volume projects (in preference to longer term and higher dollar volume projects), whereas lower discount rates allow substandard projects that may be a drag on corporate earnings. Either excess is deleterious, but the excessively high discount rate is clearly more harmful.
- Some firms use mid-year discounting (rather than end-of-year discounting) as being more realistic.[1] Some firms use continuous rather than annual discounting.
- Although the final cumulative net present value can only be determined by projecting the cash flow model out through the full life of the field, the final few years will typically represent only a small fraction of its worth. Ordinarily, a field production model of about 15 years will be adequate for most purposes, except in the case of very large fields or in cases of "late" enhanced oil recovery (EOR) projects on older fields.
- The present value of most projects will decrease as successively higher corporate discount rates are utilized. The exception would be an acceleration project[2]. The discount rate at which the present value is zero is called the discounted cash flow rate of return.
- All figures and estimates should be objective. You should neither purposefully overestimate (to sell the deal) nor underestimate (to be conservative and thereby protect yourself from being wrong). Be professional, give it your best shot
- It is a good idea to make several cash flow "cases" using different assumptions for reserves, number of wells, initial potentials (IPs), and decline rates. This is easy to do using modern software. Such sensitivity analyses give the decision maker a better idea of the range of possibilities for project outcomes. However, one shortcoming of many sensitivity analyses is that no probability of occurrence can be assigned to a given case. As a result, the decision maker has an idea of the range of possible outcomes, but no sense of the chance of occurrence of any one outcome Fortunately, this deficiency is readily correctable by using probabilistic ranges for key variables and Monte Carlo simulation to combine such variables. (For more information on ranges and probabilities, see the chapter on "Uncertainties Impacting Reserves, Revenue, and Costs.")
- A final step from such sensitivity analyses is the identification of critical threshold values necessary for the project to be commercial. In particular, requisite values for net pay, porosity, and initial production rate may be crucial in helping the well site geologist or engineer to make critical decisions on testing, stimulation, completion, or abandonment. These predetermined values should accompany the geologist or engineer to the well site.
- There are many commercial computer programs available for both mainframe and microcomputer hardware that carry out cash flow modeling routinely and quickly, allowing many different values to be input for the significant parameters. Use of such software greatly simplifies the process of cash flow modeling once the procedure is fully understood. But for those who want to test their understanding, construct your model from scratch on a spreadsheet. It is not that hard and may prove to be an invaluable learning exercise.
See also[edit]
- Risk: expected value and chance of success
- Economics: time value of money
- Risk: dealing with risk aversion
- Economics: fundamental equations for oil and gas property evaluation
- Economics: key parameters
- Economics of property acquisitions
- Taxes
- Introduction to economics and risk assessment
- Uncertainties impacting reserves, revenue, and costs